Just an FYI for those who saw that confusing sign on Main St today near the underpass being built.
This will not impact the GO Train times at all. Glad to see that!
http://www.milton.ca/en/build/resources ... 14__3_.pdf"In order to accommodate the delivery and assembly of the final steel bridge components for the Main
Street Grade Separation, lane restrictions and intermittent road closures will be in effect from
Tuesday October 28 to Friday December 5 on Main Street East through the grade separation.
Lane restrictions will be in place daily between 9am and 4pm on Main Street East through the
grade separation, with one lane of traffic maintained at all times, except during intermittent road
closures as noted below:
Tuesday October 28: approximately 10 separate road closures (each approx. 20 min in
length) throughout the day
Friday October 31: approximately 10 separate road closures (each approx. 20 min in
length) throughout the day
Tuesday November 4: approximately 2 separate road closures (each approx. 20 minutes
in length) throughout the day
Friday November 7: approximately 2 separate road closures (each approx. 20 min in
length) throughout the day
Pay duty police officers will be onsite to assist with the management of traffic during the four days
noted above where intermittent closures will take place and traffic control personnel will be onsite for
the duration of the work period.
All traffic impacts (lane restrictions and any closures) will be limited to the hours of 9am to
4pm, Monday to Friday.
Access to all businesses on Main Street East will be maintained during construction and the Main
Street entrance to the Milton Mall will remain open. "