Production Schedule - Mattamy U documents
http://www.hawthornevillager.com/phpbb/viewtopic.php?f=1&t=949
Page 1 of 1

Author:  J & R [ Wed Jun 08, 2005 7:05 pm ]
Post subject:  Production Schedule - Mattamy U documents

Hi Everyone,
We are nearing our framewalk and want to start following along the production schedule...problem is, it's nowhere to be found!!
If anyone is able to scan the Mattamy U documents to PDF and post them, I would be very grateful! Or...can you tell me what day in the timeline the framewalk should occur, and what the next milestone is?

Thanks, thanks, thanks! :D :D

Jen E.

Author:  Derek&Ruvani [ Wed Jun 08, 2005 9:36 pm ]
Post subject:  Re: Production Schedule - Mattamy U documents

J & R wrote:
Hi Everyone,
We are nearing our framewalk and want to start following along the production schedule...problem is, it's nowhere to be found!!
If anyone is able to scan the Mattamy U documents to PDF and post them, I would be very grateful! Or...can you tell me what day in the timeline the framewalk should occur, and what the next milestone is?

Thanks, thanks, thanks! :D :D

Jen E.


Hi Jen

This was posted previously, not sure if it is still accurate or not, but should give you a rough idea of the construction timelines.

215 days Structural Selections complete
150 days Colour Selections complete
139 days Excavation
100 days Roof, Plywood complete
82 days Customer Framewalk
74 days Insulation
63 days Drywall Taped & Finished
37 days Kitchen Cabinet installed
22 days Quality Assurance
18 days Custmer PDI
0 days Closing
+7 days Sign Off PDI

Author:  NKMAC [ Thu Jun 09, 2005 8:31 am ]
Post subject: 

Hmmm, our frame walk is today... 64 days before closing... we'll be sure to ask how behind they actually are.

Nic

Author:  J & R [ Thu Jun 09, 2005 6:44 pm ]
Post subject: 

Thanks everyone for your great info! Gerald & Rocchina, congrats on your framewalk from us, your across the street neighbours. Sounds like we're not far behind you in progress, so maybe we'll be able to bump the date closer again (we were already delayed once from July 18-August17).

I drove by tonight and lots was still going on even at 6:30 pm. Our brick & siding is almost done, and it's nice to see.

Jen E. :D