J & R wrote:
Hi Everyone,
We are nearing our framewalk and want to start following along the production schedule...problem is, it's nowhere to be found!!
If anyone is able to scan the Mattamy U documents to PDF and post them, I would be very grateful! Or...can you tell me what day in the timeline the framewalk should occur, and what the next milestone is?
Thanks, thanks, thanks!
Jen E.
Hi Jen
This was posted previously, not sure if it is still accurate or not, but should give you a rough idea of the construction timelines.
215 days Structural Selections complete
150 days Colour Selections complete
139 days Excavation
100 days Roof, Plywood complete
82 days Customer Framewalk
74 days Insulation
63 days Drywall Taped & Finished
37 days Kitchen Cabinet installed
22 days Quality Assurance
18 days Custmer PDI
0 days Closing
+7 days Sign Off PDI