The issue was actually Engineered Floor Joists, not floor boards.
Which clearly makes a lot more sense
Anyways after speaking with Kim Cronk as was recommended in an earlier post, I was told there was no way that this change was possible.
All modifications to floor joists is being done off site and that kitchen modifications were no longer being offered after phase 13
I had a lengthy conversation with her and was comfortable in knowing there was nothing more that I could do and accepted that this change was no longer possible
Then, earlier this week, I received a call from our design consultant and was told that under her own initiative (she wasn't aware I spoke with Kim Cronk) she spoke with the architect and the change was accepted. We are just awaiting the paper work, but have been told that this change will be made to our kitchen
|