Hi Everyone,
We are nearing our framewalk and want to start following along the production schedule...problem is, it's nowhere to be found!!
If anyone is able to scan the Mattamy U documents to PDF and post them, I would be very grateful! Or...can you tell me what day in the timeline the framewalk should occur, and what the next milestone is?

Thanks, thanks, thanks! :D :D

Jen E.


Top
 Profile  
Reply with quote  
PostPosted: Wed Jun 08, 2005 9:36 pm 
Offline
User avatar

Joined: Mon Jul 05, 2004 7:52 pm
Posts: 470
J & R wrote:
Hi Everyone,
We are nearing our framewalk and want to start following along the production schedule...problem is, it's nowhere to be found!!
If anyone is able to scan the Mattamy U documents to PDF and post them, I would be very grateful! Or...can you tell me what day in the timeline the framewalk should occur, and what the next milestone is?

Thanks, thanks, thanks! :D :D

Jen E.


Hi Jen

This was posted previously, not sure if it is still accurate or not, but should give you a rough idea of the construction timelines.

215 days Structural Selections complete
150 days Colour Selections complete
139 days Excavation
100 days Roof, Plywood complete
82 days Customer Framewalk
74 days Insulation
63 days Drywall Taped & Finished
37 days Kitchen Cabinet installed
22 days Quality Assurance
18 days Custmer PDI
0 days Closing
+7 days Sign Off PDI

_________________
Derek & Ruvani


Top
 Profile  
Reply with quote  
 Post subject:
PostPosted: Thu Jun 09, 2005 8:31 am 
Offline
User avatar

Joined: Wed May 11, 2005 8:22 am
Posts: 492
Location: Phase 1 Lot 52 Escarpment
Hmmm, our frame walk is today... 64 days before closing... we'll be sure to ask how behind they actually are.

Nic


Top
 Profile  
Reply with quote  
 Post subject:
PostPosted: Thu Jun 09, 2005 6:44 pm 
Offline
User avatar

Joined: Fri Oct 15, 2004 1:57 pm
Posts: 194
Location: Lot 309, Hearst Blvd - Lyndhurst
Thanks everyone for your great info! Gerald & Rocchina, congrats on your framewalk from us, your across the street neighbours. Sounds like we're not far behind you in progress, so maybe we'll be able to bump the date closer again (we were already delayed once from July 18-August17).

I drove by tonight and lots was still going on even at 6:30 pm. Our brick & siding is almost done, and it's nice to see.

Jen E. :D


Top
 Profile  
Reply with quote  
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 4 posts ] 

All times are UTC - 5 hours


Who is online

Users browsing this forum: No registered users and 4 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
cron
Powered by phpBB® Forum Software © phpBB Group
[ Time : 0.020s | 10 Queries | GZIP : Off ]