I e-mailed Kelly also, asking about the Main Street Towns. this is what she said
"Thank you for your email. After speaking with our Construction Manager, I have been advised that we are anticipating a delay for your lot. Unfortunately, at this time, I’m not sure what the length of the delay will be. We are currently in the process of reviewing our construction schedule to determine a revised closing date. I do apologize that we require to delay the closing on your home, however, please know that Mattamy wants to ensure that we have adequate time to build your home to the quality standards that you would expect from Mattamy Homes.
In accordance with the guidelines of Tarion, the builder can impose a maximum of 120 days delay. We are, however, required to provide you with the following notice:
For a delay of up to 120 days, we must provide you with 65 days written notice. In this case, we would have to notify you no later than August 27, 2007.
For a delay of up to 15 days, we must provide you with 35 days written notice. In this case, we would have to notify you no later than September 26, 2007.
We may notify you in writing of a 5 day delay at any time, up to and including your scheduled closing date.
If builders follow these guidelines, compensation to the homeowner does not apply. For more information about the delay guidelines you may visit their website at
www.tarion.com. Berta, I hope this information helps. Please let me know if I can be of further assistance. "
I am guessing it will be 2 months, since that seems to be the length everyone else got delayed....... this just sucks